Prescribed in 15.408(e)

Effective Date:1 October 1997
Clause or Provision:Clause
Provision or Clause Number: 52.215-13 - Subcontractor Certified Cost or Pricing Data-Modifications

Principle Type And/Or Purpose of Contract:
Required:
Applicable:Time and Materials/Labor Hour; Facilities; Architect-Engineering; Dismantling, Demolition or Removal of Improvements; Fixed Price, Supply; Cost Reimbursement, Supply; Communication Services; Leasing of Motor Vehicles; Time & Material/Labor Hour; Cost Reimbursement, Construction; Fixed Price, Construction; Cost Reimbursement, Service; Fixed Price, Service; Cost Reimbursement, R&D; Fixed Price, R&D; Indefinite Delivery; Transportation; Utility Services
Optional:Simplified Acquisition Procedures (Excludes Micro-Purchase)
Subject:Certified Cost or Pricing Data and/or Data other than Certified
ProcurementType:Sole Source
Contract Threshold:>750,000">750,000" is not in the list (>10M, >5M, >1M, >750,000, >700,000, >500,000, >150,000, >100,000, >30,000, >25,000, ...) of allowed values for the "ContractThreshold" property.
Prescription Overview:

Prescription

(e) Subcontractor Certified Cost or Pricing Data -- Modifications. The contracting officer shall insert the clause at 52.215-13, Subcontractor Certified Cost or Pricing Data -- Modifications, in solicitations and contracts when the clause prescribed in paragraph (c) of this section is included.

Paragraph (c) reads:

(c) Price Reduction for Defective Certified Cost or Pricing Data -- Modifications. The contracting officer shall, when contracting by negotiation, insert the clause at 52.215-11, Price Reduction for Defective Certified Cost or Pricing Data -- Modifications, in solicitations and contracts when it is contemplated that certified cost or pricing data will be required from the contractor or any subcontractor (see 15.403-4) for the pricing of contract modifications, and the clause prescribed in paragraph (b) of this section has not been included.

Clause Overview:

Clause Overview

Applicability

(a) The requirements of paragraphs (b) and (c) of this clause shall— (1) Become operative only for any modification to this contract involving a pricing adjustment expected to exceed the threshold for submission of certified cost or pricing data at FAR 15.403-4; and (2) Be limited to such modifications.


(b) Before awarding any subcontract expected to exceed the threshold for submission of certified cost or pricing data at FAR 15.403-4, on the date of agreement on price or the date of award, whichever is later; or before pricing any subcontract modification involving a pricing adjustment expected to exceed the threshold for submission of certified cost or pricing data at FAR 15.403-4, the Contractor shall require the subcontractor to submit certified cost or pricing data (actually or by specific identification in writing), in accordance with FAR 15.408, Table 15-2 (to include any information reasonably required to explain the subcontractor’s estimating process such as the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data, and the nature and amount of any contingencies included in the price), unless an exception under FAR 15.403-1 applies.


(c) The Contractor shall require the subcontractor to certify in substantially the form prescribed in FAR 15.406-2 that, to the best of its knowledge and belief, the data submitted under paragraph (b) of this clause were accurate, complete, and current as of the date of agreement on the negotiated price of the subcontract or subcontract modification.


(d) The Contractor shall insert the substance of this clause, including this paragraph (d), in each subcontract that exceeds the threshold for submission of certified cost or pricing data at FAR 15.403-4 on the date of agreement on price or the date of award, whichever is later.

Important Notes/Requirements:

Applicable to sole source awards that are not exempt or no exception applies.

References and Notes

Subcontract Threshold:>750,000">750,000" is not in the list (>10M, >5M, >1M, >750,000, >700,000, >500,000, >150,000, >100,000, >30,000, >25,000, ...) of allowed values for the "SubcontractThreshold" property.
Incorporated by Reference:Yes
Uniform Contract Format:I
Editor:Marshall

Personal notes.