Prescription Overview: |
Prescription(b) The contracting officer shall insert the clause at 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts, in solicitations and indefinite-delivery contracts for services (including construction) where one or more orders issued thereunder are expected to each meet or exceed the thresholds at 4.1703. This clause is not required for actions entirely funded by DoD, contracts awarded with a generic DUNS number, or in classified solicitations, contracts, or orders[1]. |
Clause Overview: |
Clause(a) Definitions “First-tier subcontract” means a subcontract awarded directly by the Contractor for the purpose of acquiring supplies or services (including construction) for performance of a prime contract. It does not include the Contractor’s supplier agreements with vendors, such as long-term arrangements for materials or supplies that benefit multiple contracts and/or the costs of which are normally applied to a Contractor’s general and administrative expenses or indirect costs. (b) The Contractor shall report, in accordance with paragraphs (c) and (d) of this clause, annually by October 31, for services performed during the preceding Government fiscal year (October 1-September 30) under this contract for orders that exceed the thresholds established in 4.1703(a)(2). (c) The Contractor shall report the following information:
(d) The information required in paragraph (c) of this clause shall be submitted via the internet at www.sam.gov. (See SAM User Guide). If the Contractor fails to submit the report in a timely manner, the Contracting Officer will exercise appropriate contractual remedies. In addition, the Contracting Officer will make the Contractor’s failure to comply with the reporting requirements a part of the Contractor’s performance information under FAR Subpart 42.15. (e) Agencies will review Contractor reported information for reasonableness and consistency with available contract information. In the event the agency believes that revisions to the Contractor reported information are warranted, the agency will notify the Contractor no later than November 15. By November 30, the Contractor shall revise the report, or document its rationale for the agency. (f)
|