DFARS 252.236-7003 Payment for Mobilization and Preparatory Work
Prescribed in 236.570(b)(2) | |
Effective Date: | 1 January 1997 |
Clause or Provision: | Clause |
Provision or Clause Number: | S 252.236-7003 Payment for Mobilization and Preparatory Work |
Principle Type And/Or Purpose of Contract: | |
Required: | |
Applicable: | Fixed Price, Construction |
Optional: | |
Subject: | |
ProcurementType: | |
Contract Threshold: | |
Prescription Overview: |
Prescription(b) Use the following provisions and clauses in fixed-price construction contracts and solicitations as applicable— (2) When the head of the contracting activity has approved use of a separate bid item for mobilization and preparatory work, use either—
|
Clause Overview: |
ClausePAYMENT FOR MOBILIZATION AND PREPARATORY WORK (JAN 1997)(a) The Government will make payment to the Contractor under the procedures in this clause for mobilization and preparatory work under item no. ____________________.
(1) For construction plant and equipment exceeding $25,000 in value per unit (as appraised by the Contracting Officer at the work site) acquired for the execution of the work; (2) Transportation of all plant and equipment to the site; (3) Material purchased for the prosecution of the contract, but not to be incorporated in the work; (4) Construction of access roads or railroads, camps, trailer courts, mess halls, dormitories or living quarters, field headquarters facilities, and construction yards; (5) Personal services; and (6) Hire of plant.
(1) An account of the Contractor's actual expenditures; (2) Supporting documentation, including receipted bills or copies of payrolls and freight bills; and (3) The Contractor's documentation—
(d) Upon receiving a request for payment, the Government will make payment, less any prescribed retained percentage, if— (1) The Contracting Officer finds the—
(2) Payments for construction plant, equipment, material, and structures and facilities prepared or erected for prosecution of the contract work do not exceed—
(1) Payments will continue to be made for item no. _____________, and all payments will be deducted from the contract price for this item, until the total deductions reduce this item to zero, after which no further payments will be made under this item. (2) If the total of payments so made does not reduce this item to zero, the balance will be paid to the Contractor in the final payment under the contract. (3) The retained percentage will be paid in accordance with the Payments to Contractor clause of this contract.
|