DFARS 252.236-7002 Obstruction of Navigable Waterways
Prescribed in 236.570(b)(1) | |
Effective Date: | 1 December 1991 |
Clause or Provision: | Clause |
Provision or Clause Number: | S 252.236-7002 Obstruction of Navigable Waterways |
Principle Type And/Or Purpose of Contract: | |
Required: | |
Applicable: | Fixed Price, Construction |
Optional: | |
Subject: | |
ProcurementType: | |
Contract Threshold: | |
Prescription Overview: |
Prescription(b) Use the following provisions and clauses in fixed-price construction contracts and solicitations as applicable— (1) 252.236-7002, Obstruction of Navigable Waterways, when the contract will involve work near or on navigable waterways. |
Clause Overview: |
ClauseOBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991)(a) The Contractor shall— (1) Promptly recover and remove any material, plant, machinery, or appliance which the contractor loses, dumps, throws overboard, sinks, or misplaces, and which, in the opinion of the Contracting Officer, may be dangerous to or obstruct navigation; (2) Give immediate notice, with description and locations of any such obstructions, to the Contracting Officer; and (3) When required by the Contracting Officer, mark or buoy such obstructions until the same are removed.
(1) Remove the obstructions by contract or otherwise should the Contractor refuse, neglect, or delay compliance with paragraph (a) of this clause; and (2) Deduct the cost of removal from any monies due or to become due to the Contractor; or (3) Recover the cost of removal under the Contractor's bond.
|
Important Notes/Requirements: | |
Subcontract Threshold: | |
Incorporated by Reference: | Yes |
Uniform Contract Format: | |
Editor: | Marshall |
Personal notes.