DFARS 252.217-7003 Changes
Prescribed in 217.7104(a) | |
Effective Date: | 1 December 1991 |
Clause or Provision: | Clause |
Provision or Clause Number: | S 252.217-7003 Changes |
Principle Type And/Or Purpose of Contract: | |
Required: | |
Applicable: | |
Optional: | |
Subject: | |
ProcurementType: | |
Contract Threshold: | |
Prescription Overview: |
Prescription(a) Use the following clauses in solicitations for, and in, master agreements for repair and alteration of vessels:
|
Clause Overview: |
ClauseCHANGES (DEC 1991)(a) The Contracting Officer may, at any time and without notice to the sureties, by written change order, make changes within the general scope of any job order issued under the Master Agreement in—
(b) If a change causes an increase or decrease in the cost of, or time required for, performance of the job order, whether or not changed by the order, the Contracting Officer shall make an equitable adjustment in the price or date of completion, or both, and shall modify the job order in writing.
(c) If the Contractor includes in its claim the cost of property made obsolete or excess as a result of a change, the Contracting Officer shall have the right to prescribe the manner of disposition of that property.
(d) Failure to agree to any adjustment shall be a dispute within the meaning of the Disputes clause.
(e) Nothing in this clause shall excuse the Contractor from proceeding with the job order as changed. |
Important Notes/Requirements: | |
Subcontract Threshold: | |
Incorporated by Reference: | Yes |
Uniform Contract Format: | |
Editor: | Marshall |