DFARS 252.209-7009, Organizational Conflict of Interest—Major Defense Acquisition Program
Prescribed in 209.571-8(b) | |
Effective Date: | 1 December 2012 |
Clause or Provision: | Clause |
Provision or Clause Number: | S 252.209-7009, Organizational Conflict of Interest—Major Defense Acquisition Program |
Principle Type And/Or Purpose of Contract: | |
Required: | |
Applicable: | |
Optional: | |
Subject: | |
ProcurementType: | |
Contract Threshold: | |
Prescription Overview: |
Prescription(b) Use the clause at 252.209-7009, Organizational Conflict of Interest—Major Defense Acquisition Program, in solicitations and contracts for systems engineering and technical assistance for major defense acquisition programs or pre-major defense acquisition programs. |
Clause Overview: |
ClauseORGANIZATIONAL CONFLICT OF INTEREST—MAJOR DEFENSE ACQUISITION PROGRAM (DEC 2012)(a) Definition“Major subcontractor,” as used in this clause, means a subcontractor that is awarded a subcontract that equals or exceeds—
Purpose(b) This contract is for the performance of systems engineering and technical assistance for a major defense acquisition program or a pre-major defense acquisition program.
(c) ProhibitionExcept as provided in paragraph (d) of this clause, as required by paragraph (b)(3) of section 207 of the Weapons System Acquisition Reform Act of 2009 (Pub. L. 111-23), the Contractor or any affiliate of the Contractor is prohibited from participating as a prime contractor or major subcontractor in the development or production of a weapon system under the major defense acquisition program or pre-major defense acquisition program.
(d) Organizational Conflict of Interest Mitigation PlanIf the Contractor submitted an acceptable Organizational Conflict of Interest Mitigation Plan that has been incorporated into this contract, then the prohibition in paragraph (c) of this clause does not apply. The Contractor shall comply with the Organizational Conflict of Interest Mitigation Plan. Compliance with the Organizational Conflict of Interest Mitigation Plan is a material requirement of the contract. Failure to comply may result in the Contractor or any affiliate of the Contractor being prohibited from participating as a contractor or major subcontractor in the development or production of a weapon system under the program, in addition to any other remedies available to the Government for noncompliance with a material requirement of a contract. |
Important Notes/Requirements: | |
Subcontract Threshold: | |
Incorporated by Reference: | Yes |
Uniform Contract Format: | |
Editor: | Marshall |