DFARS 252.247-7012 Ordering Limitation
Prescribed in 247.271-3(g) | ||
Effective Date: | 1 December 1991 | |
Clause or Provision: | Clause | |
Provision or Clause Number: | S 252.247-7012 Ordering Limitation | |
Principle Type And/Or Purpose of Contract: | ||
Required: | ||
Applicable: | ||
Optional: | ||
Subject: | ||
ProcurementType: | ||
Contract Threshold: | ||
Prescription Overview: |
Prescription | |
Clause Overview: |
ClauseORDERING LIMITATION (DEC 1991)(a) The Government will place orders for items of supplies or services with the contractor awarded the initial contract to the extent of the contractor's guaranteed maximum daily capability. However, the contractor may accept an additional quantity in excess of its capability to accommodate a single order.
| |
Important Notes/Requirements: | ||
Subcontract Threshold: | ||
Incorporated by Reference: | Yes | |
Uniform Contract Format: | ||
Editor: | Marshall |
Personal notes.