FAR 52.244-2 - Subcontracts

From Knowledge base
Revision as of 15:13, 8 May 2014 by Marshall (Talk | contribs)

Jump to: navigation, search
***

Prescribed in 44.204(a)(1)

Effective Date:1 May 2014
Clause or Provision:Clause
Provision or Clause Number: 52.244-2 - Subcontracts

Principle Type And/Or Purpose of Contract:
Required:
Applicable:Fixed Price Service; Cost Reimbursement Research and Development; Fixed Price Research and Development; Cost Reimbursement Supply; Fixed Price Supply; Cost Reimbursement Service; Fixed Price Construction; Cost Reimbursement Construction; Time and Materials/Labor Hour; Leasing of Motor Vehicles; Communication Services; Dismantling, Demolition, or Removal of Improvements; Architect-Engineering; Facilities; Indefinite Delivery; Transportation; Utility Services; 
Optional:Simplified Acquisition Procedures; 
Subject:
ProcurementType:
Contract Threshold:>150,000
Prescription Overview:
Clause Overview:

The contract clause FAR 52.244-2 requires a contractor that does not have an approved purchasing system to obtain consent, when:

  • 1. The contract is a cost-reimbursement, time-and-materials, or labor-hour type, or
  • 2. Is fixed price and exceeds:
    • i. A Department of Defense, Cost Guard, or National Aeronautics and Space Administration, the greater of the simplified acquisition threshold or 5% of the total estimated cost of the contract, or
    • ii. For a contract awarded by a civilian agency other than the ones noted above, either the simplified acquisition threshold or 5% of the total estimated cost of the contract.
Important Notes/Requirements:

Also See - Consent to Subcontract

Subcontract Threshold:>150,000
Incorporated by Reference:Yes
Uniform Contract Format:I