− | '''(f)''' At any time during contract performance, but no later than 6 months (or such other time as may be specified in the contract) after acceptance of the supplies to be delivered under the contract, '''the Government may require the Contractor to replace or correct any supplies that are nonconforming at time of delivery. Supplies are nonconforming when they are defective in material or workmanship or are otherwise not in conformity with contract requirements.''' Except as otherwise provided in paragraph (h) of this clause, the cost of replacement or correction shall be included in allowable cost, determined as provided in the Allowable Cost and Payment clause, but no additional fee shall be paid. The Contractor shall not tender for acceptance supplies required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken. | + | '''(f)''' At any time during contract performance, but no later than 6 months (or such other time as may be specified in the contract) after acceptance of the supplies to be delivered under the contract, '''the Government may require the Contractor to replace or correct any supplies that are nonconforming at time of delivery. Supplies are nonconforming when they are defective in material or workmanship or are otherwise not in conformity with contract requirements.''' '''Except as otherwise provided in paragraph (h) of this clause, the cost of replacement or correction shall be included in allowable cost, determined as provided in the Allowable Cost and Payment clause, but no additional fee shall be paid.''' The Contractor shall not tender for acceptance supplies required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken. |
Latest revision as of 15:41, 6 August 2020
Prescribed in 46.303 | ||
Effective Date: | 1 May 2001 | |
Clause or Provision: | Clause | |
Provision or Clause Number: | 52.246-3 - Inspection of Supplies—Cost-Reimbursement | |
Principle Type And/Or Purpose of Contract: | ||
Required: | ||
Applicable: | Cost Reimbursement, Supply; Cost Reimbursement, Service; Cost Reimbursement, R&D | |
Optional: | Utility Services; Simplified Acquisition Procedures (Excludes Micro-Purchase); Facilities; Indefinite Delivery; Dismantling, Demolition or Removal of Improvements; Leasing of Motor Vehicles; Fixed Price, Construction; Time & Material/Labor Hour; Cost Reimbursement, Construction; Fixed Price, Service | |
Subject: | ||
ProcurementType: | ||
Contract Threshold: | ||
Prescription Overview: |
Prescription | |
Clause Overview: |
Insertion RequirementAs prescribed in 46.303, insert the following clause in solicitations and contracts for supplies, or services that involve the furnishing of supplies, when a cost-reimbursement contract is contemplated: Clause(a) Definitions As used in this clause— “Contractor’s managerial personnel” means any of the Contractor’s directors, officers, managers, superintendents, or equivalent representatives who have supervision or direction of—
“Supplies” includes but is not limited to raw materials, components, intermediate assemblies, end products, lots of supplies, and, when the contract does not include the Warranty of Data clause, data.
| |