Difference between revisions of "Public Vouchers"

From Knowledge base
Jump to: navigation, search
 
(2 intermediate revisions by one user not shown)
Line 1: Line 1:
 
==DCAA Public Voucher Guidance==
 
==DCAA Public Voucher Guidance==
 +
 +
==Introduction==
 +
 +
Cost type contracts provide for interim payments for costs on a Standard Form (SF) 1034 public voucher or equivalent.
 +
DCAA will perform voucher reviews based on risk.
 +
 +
• Fixed price contracts are subject to FAR Part 32 financing methods.
 +
 +
==Contractor Responsibilities==
 +
 +
* Contact the cognizant DCAA office after contract award
 +
 +
• Ensure DCAA has the necessary information to process contract billings, such as current provisional billing rates, copy of the contract, any special contract provisions, etc.
 +
 +
• Maintain adequate billing system internal controls
 +
 +
• Ensure adequate support is maintained for amounts billed
 +
 +
• Submit timely incurred cost proposals and final vouchers in accordance with FAR 52.216-7
  
 
===DCAA Responsibilities - Pre-Payment Review of Vouchers===
 
===DCAA Responsibilities - Pre-Payment Review of Vouchers===
Line 19: Line 38:
 
• Review monitoring of subcontracts in accordance with FAR 42.202(e)(2)
 
• Review monitoring of subcontracts in accordance with FAR 42.202(e)(2)
  
File:DCAA_Public_Voucher_Guidance.pdf
+
 
  
 
[[File:DCAA_Public_Voucher_Guidance.pdf]]
 
[[File:DCAA_Public_Voucher_Guidance.pdf]]
 +
 +
  
 
== Links ==
 
== Links ==

Latest revision as of 21:15, 9 February 2021

Contents

DCAA Public Voucher Guidance

Introduction

Cost type contracts provide for interim payments for costs on a Standard Form (SF) 1034 public voucher or equivalent. DCAA will perform voucher reviews based on risk.

• Fixed price contracts are subject to FAR Part 32 financing methods.

Contractor Responsibilities

  • Contact the cognizant DCAA office after contract award

• Ensure DCAA has the necessary information to process contract billings, such as current provisional billing rates, copy of the contract, any special contract provisions, etc.

• Maintain adequate billing system internal controls

• Ensure adequate support is maintained for amounts billed

• Submit timely incurred cost proposals and final vouchers in accordance with FAR 52.216-7

DCAA Responsibilities - Pre-Payment Review of Vouchers

• Evaluate for compliance with contract terms and billing instructions

• Reconcile billed costs to the accounting records

• Verify that indirect costs are calculated using established provisional billing rates

• Verify the voucher is properly prepared (mathematically accurate, contains cumulative costs, etc.)

• Verify timely payments to vendors and subcontractors

• Verify billed labor, materials, and other direct costs to accounting records and supporting documentation

• Compare amount billed to amount received

• Review monitoring of subcontracts in accordance with FAR 42.202(e)(2)


File:DCAA Public Voucher Guidance.pdf