Line 2: | Line 2: | ||
|EffectiveDate=1996/09/01 | |EffectiveDate=1996/09/01 | ||
|ClauseorProvision=Clause | |ClauseorProvision=Clause | ||
− | |||
|Prescribedin=28.101-2 | |Prescribedin=28.101-2 | ||
− | |TypePurposeContract= | + | |TypePurposeContract=Time and Materials/Labor Hour -A |
− | | | + | |TypeofContractApplicable=Facilities; Architect-Engineering; Dismantling, Demolition or Removal of Improvements; Fixed Price, Supply; Cost Reimbursement, Supply; Communication Services; Leasing of Motor Vehicles; Time & Material/Labor Hour; Cost Reimbursement, Construction; Fixed Price, Construction; Cost Reimbursement, Service; Fixed Price, Service; Cost Reimbursement, R&D; Fixed Price, R&D; Indefinite Delivery; Transportation; Simplified Acquisition Procedures (Excludes Micro-Purchase); Utility Services |
− | |FARClauseOverview='''(a)''' Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid. | + | |CCSubject=Bid & Proposal |
+ | |PrescriptionOverview===Prescription== | ||
+ | |||
+ | '''(a)''' The contracting officer shall insert a provision or clause substantially the same as the provision at 52.228-1, Bid Guarantee, in solicitations or contracts that require a bid guarantee or similar guarantee. For example, the contracting officer may modify this provision— | ||
+ | |||
+ | |||
+ | (1) To set a period of time that is other than 10 days for the return of executed bonds; | ||
+ | |||
+ | |||
+ | (2) For use in connection with construction solicitations when the agency has specified that only separate bid bonds are acceptable in accordance with 28.101-1(b); | ||
+ | |||
+ | |||
+ | (3) For use in solicitations for negotiated contracts; or | ||
+ | |||
+ | |||
+ | (4) For use in service contracts containing options for extended performance. | ||
+ | |||
+ | |||
+ | '''(b)''' The contracting officer shall determine the amount of the bid guarantee for insertion in the provision at 52.228-1 (see 28.102-2(a)). The amount shall be adequate to protect the Government from loss should the successful bidder fail to execute further contractual documents and bonds as required. The bid guarantee amount shall be at least 20 percent of the bid price but shall not exceed $3 million. When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated. | ||
+ | |FARClauseOverview===Clause== | ||
+ | |||
+ | '''(a)''' Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid. | ||
Line 20: | Line 40: | ||
− | '''(e)''' In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference. | + | '''(e)''' In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference. |
− | + | ||
|ImportantNotesRequirements=Requires bidder to furnish a bid guarantee in the form of a firm commitment, e.g., bid bond, postal money order, certified check, cashier's check, irrevocable letter of credit, etc. | |ImportantNotesRequirements=Requires bidder to furnish a bid guarantee in the form of a firm commitment, e.g., bid bond, postal money order, certified check, cashier's check, irrevocable letter of credit, etc. | ||
More commonly found in contracts for construction or professional engineering & design solicitations. | More commonly found in contracts for construction or professional engineering & design solicitations. | ||
+ | |||
+ | [[Category:FAR 52 - Solicitation Provisions and Contract Clauses]] | ||
|IncorporatedbyReference=Yes | |IncorporatedbyReference=Yes | ||
|UniformContractFormat=I | |UniformContractFormat=I | ||
|Editor=Marshall | |Editor=Marshall | ||
+ | |ProvisionClauseNumberAlternate=52.228-1 | ||
+ | |ProvisionClauseDescription=- | ||
|Checked=no | |Checked=no | ||
|HasTermDate=2014/03/31 | |HasTermDate=2014/03/31 |
Latest revision as of 09:24, 28 December 2014
Prescribed in 28.101-2 | |
Effective Date: | 1 September 1996 |
Clause or Provision: | Clause |
Provision or Clause Number: | 52.228-1 - Bid Guarantee |
Principle Type And/Or Purpose of Contract: | |
Required: | |
Applicable: | Time and Materials/Labor Hour; Facilities; Architect-Engineering; Dismantling, Demolition or Removal of Improvements; Fixed Price, Supply; Cost Reimbursement, Supply; Communication Services; Leasing of Motor Vehicles; Time & Material/Labor Hour; Cost Reimbursement, Construction; Fixed Price, Construction; Cost Reimbursement, Service; Fixed Price, Service; Cost Reimbursement, R&D; Fixed Price, R&D; Indefinite Delivery; Transportation; Simplified Acquisition Procedures (Excludes Micro-Purchase); Utility Services |
Optional: | |
Subject: | Bid & Proposal |
ProcurementType: | |
Contract Threshold: | |
Prescription Overview: |
Prescription(a) The contracting officer shall insert a provision or clause substantially the same as the provision at 52.228-1, Bid Guarantee, in solicitations or contracts that require a bid guarantee or similar guarantee. For example, the contracting officer may modify this provision—
|
Clause Overview: |
Clause(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
|
Important Notes/Requirements: |
Requires bidder to furnish a bid guarantee in the form of a firm commitment, e.g., bid bond, postal money order, certified check, cashier's check, irrevocable letter of credit, etc. More commonly found in contracts for construction or professional engineering & design solicitations. |
Subcontract Threshold: | |
Incorporated by Reference: | Yes |
Uniform Contract Format: | I |