Difference between revisions of "FAR 52.244-2 - Subcontracts"
From Knowledge base
m (1 revision) |
|||
Line 1: | Line 1: | ||
{{ContractClause | {{ContractClause | ||
+ | |EffectiveDate=2014/05/01 | ||
+ | |ClauseorProvision=Clause | ||
+ | |ProvisionClauseNumberAlternate=52.244-2 | ||
+ | |Prescribedin=44.204(a)(1) | ||
+ | |TypePurposeContract=Fixed Price Service -A; Cost Reimbursement Research and Development -A; Fixed Price Research and Development -A; Cost Reimbursement Supply -A; Fixed Price Supply -A; Cost Reimbursement Service -A; Fixed Price Construction -A; Cost Reimbursement Construction -A; Time and Materials/Labor Hour -A; Leasing of Motor Vehicles -A; Communication Services -A; Dismantling, Demolition, or Removal of Improvements -A; Architect-Engineering -A; Facilities -A; Indefinite Delivery -A; Transportation -A; Simplified Acquisition Procedures -O; Utility Services -A | ||
+ | |ProvisionClauseDescription=Subcontracts. | ||
+ | |ImportantNotesRequirements=Also See - [[Consent to Subcontract]] | ||
+ | |IncorporatedbyReference=Yes | ||
+ | |UniformContractFormat=I | ||
+ | |Editor=Marshall | ||
|Checked=no | |Checked=no | ||
|HasTermDate=2014/03/31 | |HasTermDate=2014/03/31 | ||
− | |||
− | |||
|ProvisionClauseNumber=52.244-2 | |ProvisionClauseNumber=52.244-2 | ||
− | |||
|RegulationSection=44 | |RegulationSection=44 | ||
− | |||
|FunctionalTopicalArea= | |FunctionalTopicalArea= | ||
− | |||
− | |||
− | |||
− | |||
− | |||
|FARCitation= | |FARCitation= | ||
− | |||
|ImportantCaseLaw= | |ImportantCaseLaw= | ||
− | |||
|FlowClauses= | |FlowClauses= | ||
− | |||
− | |||
− | |||
}} | }} |
Revision as of 15:06, 8 May 2014
Prescribed in 44.204(a)(1) | |
Effective Date: | 1 May 2014 |
Clause or Provision: | Clause |
Provision or Clause Number: | 52.244-2 - Subcontracts |
Principle Type And/Or Purpose of Contract: | |
Required: | |
Applicable: | Fixed Price Service; Cost Reimbursement Research and Development; Fixed Price Research and Development; Cost Reimbursement Supply; Fixed Price Supply; Cost Reimbursement Service; Fixed Price Construction; Cost Reimbursement Construction; Time and Materials/Labor Hour; Leasing of Motor Vehicles; Communication Services; Dismantling, Demolition, or Removal of Improvements; Architect-Engineering; Facilities; Indefinite Delivery; Transportation; Utility Services; |
Optional: | Simplified Acquisition Procedures; |
Subject: | |
ProcurementType: | |
Contract Threshold: | |
Prescription Overview: | |
Clause Overview: | |
Important Notes/Requirements: |
Also See - Consent to Subcontract |
Subcontract Threshold: | |
Incorporated by Reference: | Yes |
Uniform Contract Format: | I |
Editor: | Marshall |
Personal notes.